iE
PMG LlancayObton · iEnergia O&M
FO INSTALLED
GPM Session Jun 15
PMG Llancay · Executive Briefing · Jun 2026

Integration Delay
Root Cause Analysis

Fiber optic was mandatory per CEN/GPM — not optional. iEnergia drove the resolution. CGE design criteria caused a 2-month delay. Open loop = monitoring ≠ PPC control.

~2.5mo
Total Delay
<30min
iEnergia Response Time
Jun 11
FO Installed
Jun 15
GPM PPC Session
Press ESC or click Present to exit
Executive Dashboard · iEnergia Internal · Updated 13 Jun 2026

PMG Llancay
Integration Analysis

Complete record of the meter integration process: why it took 2.5 months, what was tried, who did what, and why fiber optic was the only viable path to CEN certification.

S/E El Peumo, Paño E5  ·  ION 8650 at POI  ·  O&M: iEnergia  ·  Client: Obton
Jun 11
Fiber Optic Installed
S/E El Peumo · FENIX IO SPA
~2.5mo
Total Integration Delay
Mar 31 GPM mandate → Jun 11 FO done
<30min
iEnergia Response Time
Any technical question received → answered
Jun 15
GPM PPC Session
Ticket #89466 · Emmanuel Honorato
Jun 18
CEN Coordinator Tests
Connection tests · strict audit
FO Rejections by CGE
First route blocked by design criteria
Full Project Timeline

From GPM Mandate to Fiber Optic

Extended timeline from March 2026 GPM declaration that FO was mandatory through installation and upcoming CEN tests.

Oct 2025
RUTX11 Installed
RNE / Verbux
!
Mar 31 2026
GPM Declares FO Mandatory
Surprise to all parties
Apr 30 2026
Alexander Asks CGE
Obton → CGE · emergency basis
May 5 2026
CGE Rejects First Route
Design criteria violation
!
May 28 2026
Comms Loss & Recovery
RUTX11 reset · iEnergia + RNE
Jun 3 2026
CGE Approves New Route
2 new chambers · segregated conduit
Jun 10 2026
iEnergia Network Docs Sent
Emilio → Alexander/GPM
Jun 11–12 2026
Fiber Optic Installed
FENIX IO SPA · civil works
Jun 15 2026
GPM PPC Modification
GPM #89466
Jun 18 2026
CEN Coordinator Tests
CEN · no-delay audit
Root Cause Analysis

Why It Took 2.5 Months

The delay was not due to inaction. It was caused by a sequence of technical constraints and regulatory blocks — each one logically forcing the next — with multiple parties involved. iEnergia drove resolution at every step where it had authority.

1
Oct 2025 – Mar 2026 · Background state
GPM Was Reading the Meter — But Not Using It as PPC Input
GPM (GreenPowerMonitor) had successfully integrated the ION 8650 into SCADA monitoring via the USR RS485→Ethernet converter (192.168.1.7:502, unit 103). Polling every 5 minutes, all values visible. GPM confirmed everything was working. This is the "working" state that would later cause confusion — monitoring and PPC control are different requirements.
!
March 31, 2026 · The pivot
GPM Declares Fiber Optic Mandatory for PPC Certification
GPM informed Obton that the existing RS485/Modbus TCP communication path was not viable for the control-loop requirements of the PPC tests with the CEN Coordinator. Fiber optic was mandatory — not a preference. This was a surprise at this stage of the process.
"GPM nos informó que ciertos controles requeridos para dichas pruebas no son técnicamente viables con nuestra configuración actual, y que se requiere obligatoriamente una conexión de fibra óptica (FO) para poder proceder. Esto nos tomó por sorpresa dado lo avanzado del proceso."
— Alexander Carthew (Obton) to CGE, Apr 30 2026
2
April 30, 2026 · Obton escalates
Obton Contacts CGE on Emergency Basis to Request FO Authorization
Alexander Carthew (Obton) formally contacted CGE to request authorization for installing the fiber optic line inside S/E El Peumo. This was described as urgent given the stage of the connection process with the CEN Coordinator.
May 5, 2026 · First blocker
CGE Rejects the Proposed FO Route — Design Criteria Violation
Adonis Fuenzalida (CGE) formally rejected the initial FO installation proposal. The reason: the proposed route passed through the MT chamber N°1 (medium-voltage cables corridor), and CGE's substation design criteria explicitly prohibit mixing force systems with control/communications wiring in the same conduit.
"La solución propuesta por PMG Llancay incumple lo establecido por el Coordinador Eléctrico en el documento 'Criterio de Diseño de Subestaciones', el cual señala que no deben compartirse sistemas de fuerza y control."
— Adonis Fuenzalida, CGE · May 5, 2026
This forced a complete redesign: two new chambers were required to route the FO in a fully segregated conduit, away from any medium-voltage cabling.
!
May 28, 2026 · Incident
Comms Loss — RUTX11 Needed Reset
The Teltonika RUTX11 (RNE's router) lost connectivity. iEnergia detected it immediately: plant data and equipment remained online on our side. Adan Colina (iEnergia) contacted RNE and confirmed the issue was in their router — not in the meter or gateway.
"Por nuestra parte contamos con datos y equipos en línea, el problema puede estar en su router."
— Adan Colina, iEnergia → RNE · May 28, 2026
3
June 3, 2026 · Redesign approved
CGE Approves Revised FO Route with Two New Chambers
After redesigning the route with two new concrete chambers and fully segregated conduit (no shared systems), CGE approved the proposal and authorized civil works for June 11–12.
"La propuesta fue aprobada. Desde zona nos indican que se procederá con la tramitación de los permisos para las obras civiles programadas para los días 11 y 12 del presente mes."
— CGE · June 3, 2026
4
June 8, 2026 · Decision confirmed
Alexander Reactivates GPM — Confirms FO Decision, ~2 Hours of Programming Left
After the GPM session had gone quiet, Alexander contacted GPM to confirm the FO was coming and requested they resume programming work.
"Como hablé con Daniel antes, tomemos la decisión para instalar una línea de FO... Entiendo que solo queda un par de horas de programación para terminar el PPC cuando tenemos la fibra óptica instalada."
— Alexander Carthew (Obton) → GPM · June 8, 2026
5
June 11–12, 2026 · Resolution
Fiber Optic Installed at S/E El Peumo — Civil Works Complete
FENIX IO SPA (Eduardo Alvarez) completed installation of ZTT ADSS-SS-URBANO monomode G.652D fiber optic cable within the S/E El Peumo perimeter. Route uses the newly approved segregated conduit with two new chambers. Works completed over two days.
Bottom Line on Delay

The delay was caused by: (1) GPM's March 31 requirement that arrived late in the process, (2) CGE's first route rejection which added ~4 weeks of redesign, (3) civil works permitting and scheduling. None of these were within iEnergia's control. iEnergia's role — maintaining the meter connection live, answering technical questions, diagnosing the May 28 comms loss — was executed without delay at every step.

Phase 0 — Before the FO Mandate

What iEnergia Built First

Before GPM declared fiber optic mandatory in March 2026, iEnergia had already done substantial investigative and integration work: physically locating the meter, researching manuals, configuring RS485, installing a control board, coordinating with RNE for their Teltonika installation, and successfully completing SITR testing. This is the foundation the current project stands on.

1
Early phase · physical investigation
Network Investigation at S/E El Peumo — Finding the Meter
iEnergia conducted on-site investigation at S/E El Peumo to locate the ION 8650 meter in Paño E5 and map the existing communication infrastructure. The investigation identified two distinct network segments that would later define the entire project architecture: the POI LAN (192.168.1.0/24) under iEnergia/plant control, and the CGE/RNE segment (10.13.19.0/24) used for regulatory reporting. Identifying this dual-network reality early was critical — it meant the team knew from the start which paths were available and which were off-limits.
2
Manual research phase
ION 8650 Manual Research — Determining RS485 Configuration
iEnergia obtained and reviewed Schneider Electric ION 8650 documentation to determine the meter's communication port configuration. The meter supports RS485 serial communication via its COM port. iEnergia established the correct parameters:
RS485 Configuration (from manual research):
Port: COM4  ·  Protocol: Modbus RTU  ·  Baud rate: 9600  ·  Data: 8N1  ·  Unit ID: 103
These exact parameters, confirmed by iEnergia through manual research, were what Emilio provided to GPM on Jun 10 2026 within 30 minutes of Alexander's request.
3
Physical installation
Control Board Installed at Substation — RS485 to Ethernet Conversion
iEnergia installed the USR RS485→Ethernet converter (USR brand gateway) inside the POI cabinet at S/E El Peumo, along with associated switching equipment and a dedicated control board. This created the POI LAN segment (192.168.1.0/24) that serves as the plant's own communication backbone. The gateway was configured at 192.168.1.7:502 with Unit ID 103, bridging the meter's RS485 port to TCP/IP for GPM's SCADA integration.
4
RS485 integration — confirmed working
RS485 Integration Validated — GPM SCADA Reads Meter
After the USR gateway installation, iEnergia commissioned the RS485 link and validated it end-to-end with GPM. GPM confirmed that the SCADA element LLY_POI / ION_8650 was successfully polling meter values via 192.168.1.7:502. All electrical measurements from the ION 8650 — active power, reactive power, voltage, current, frequency — visible in GPM's SCADA. This is what GPM referred to as "everything working" — and it was, for monitoring purposes. This path remains active today, providing 5-minute interval data for O&M.
5
Oct 2025 · RNE collaboration
RNE Collaboration — Teltonika RUTX11 Installation for Recloser & Meter Ethernet Access
iEnergia coordinated with RNE (Red Nacional Eléctrica / Reliable) to install a Teltonika RUTX11 cellular router at S/E El Peumo. The installation was carried out by Verbux (Juan Cuevas) under RNE's direction. The purpose was dual: (1) give RNE's control center remote access to the recloser at Paño E5 (10.13.19.39) and (2) give RNE access to meter data via the ION 8650 Ethernet port (10.13.19.38) for SITR and CEN regulatory reporting. iEnergia participated in the technical coordination to ensure the RNE segment (10.13.19.x) integrated correctly with the substation equipment without interfering with the plant's own POI LAN.
Devices on RNE's segment after installation:
10.13.19.38 — ION 8650 Ethernet port (meter → CGE/CEN reporting)
10.13.19.39 — Recloser E5 (Form 6 recloser, remote access for RNE)
10.13.19.x — Teltonika RUTX11 LAN IP · Movistar 4G WAN
6
SITR testing · CEN reporting path
SITR Testing Successful — CEN Reporting Path Confirmed Working
With the RUTX11 and meter Ethernet in place, iEnergia organized and supported the SITR (Sistema de Información en Tiempo Real) connection testing with the CEN Coordinator. iEnergia coordinated the test scheduling, provided technical support during testing, and confirmed that the CEN's data reporting path via 10.13.19.38 → RUTX11 → Movistar 4G → CEN was operational. SITR testing passed. The CEN's real-time telemetry link for the plant was certified. This established Llancay's compliance with CEN metering reporting requirements — separate from, and prior to, the PPC control certification requirement that came later.
"SITR test success established that the data reporting path was compliant. The PPC certification that followed later requires an additional control path — different requirements, different infrastructure."
Context: What Was Already Operational Before the FO Mandate

By the time GPM declared FO mandatory in March 2026, iEnergia had already: investigated the site network, researched the ION 8650 manuals, installed the control board and RS485 gateway, validated SCADA monitoring (working), coordinated RNE's Teltonika installation, and successfully completed SITR testing for CEN reporting. The project was not starting from zero in March 2026 — it was well advanced in monitoring and reporting, and only the PPC control-loop certification step required the FO.

RS485 Path (iEnergia)
Operational since Oct 2025
USR gateway 192.168.1.7:502 · Unit 103 · 9600 8N1 · 5-min poll · GPM SCADA confirmed. Built and maintained by iEnergia.
RNE Ethernet Path (CGE-side)
Operational since Oct 2025
RUTX11 → 10.13.19.38 (meter) + 10.13.19.39 (recloser) · Movistar 4G · managed by RNE. iEnergia coordinated installation.
Fiber Optic Path (PPC)
Installed Jun 11–12 2026
ZTT ADSS G.652D · FENIX IO SPA · segregated conduit · CGE-approved route. Required for PPC certification. ~2hrs GPM programming remaining.
EO/VMD Testing — The Final Test That Failed

GME Audit: Why the Tests Couldn't Pass

The EO (Entrada en Operación) and VMD (Validación del Modelo Dinámico) tests are the formal CEN entry-into-operation certification tests, conducted by GME (gme-global.com), an independent technical firm. These tests are the final gate before a plant is certified as operational. The sequence of events from January to March 2026 shows exactly how the project reached a critical inflection point.

What are EO/VMD Tests?
  • EO — Entrada en Operación
    CEN regulatory requirement for all new generators. Tests entry into operation parameters: power ramp rates, frequency response, active power control.
  • VMD — Validación del Modelo Dinámico
    Validates that the plant's dynamic model matches real behavior. Requires actual closed-loop responses — voltage control, reactive power, frequency droop — to match the submitted CEN model.
  • GME (gme-global.com)
    Independent certification company. Nicolas Perez (Renewable Technical Integration Leader) and Pablo Bobenrieth. They run the tests under strict CEN protocol — not flexible, not negotiable.
What GME Requires (Per CEN Protocol)
  • Active power reduction under over-frequency
    Control de reducción de potencia ante sobrefrecuencia — must respond dynamically to frequency events
  • Voltage control (closed-loop)
    Real-time voltage reference tracking — requires live meter signal at POI, not simulated values
  • Reactive power response
    Voltage and reactive power set-point changes must be demonstrated with real measurements
  • Proof before tests start
    GME required screenshots of voltage/reactive reference changes before agreeing to attend. After one failed attempt, they required hard proof upfront.
1
Jan 7–13, 2026 · GME kickoff
GME Reviews Data — "La grabación se ve correcta para hacer las pruebas"
GME (Nicolas Perez) reviews the recordings and 1-second data files submitted by Vector Renewables (Fabiola Silva). GME confirms the data format is acceptable and gives the green light to schedule CEN test dates. Fabiola coordinates directly with the CEN Coordinator to request dates. Emilio Toledo (iEnergia) is in CC throughout.
"La grabación se ve correcta como para hacer las pruebas."
— Nicolas Perez (GME) · Jan 13, 2026
2
Sep 2025 – Feb 2026 · GPM PPC configuration (Diego Allende)
Diego Allende (GPM) Declares Llancay Pending Items Complete — SCADA Integration
Diego Allende (Technical Project Manager, GreenPowerMonitor / DNV) confirmed all pending Llancay SCADA integration items were finished: analog signals, PPC values, active power control status, switchgear readings. This is a SCADA monitoring completion, not a PPC control-loop certification. The critical distinction: the PPC was configured with a "medidor ficticio" (fictitious meter) — simulated values from inverter averages — for frequency and reactive power, with fixed values for voltage.
"Quisiera informar que ya finalizamos los pendientes correspondientes al proyecto Llancay: Señales analógicas · Valores PPC · Estado de control de potencia activa · Lecturas switchgear."
— Diego Allende (GPM/DNV) · Sep/Oct 2025
⚠ This was about SCADA integration. It was not a statement that the PPC would pass CEN EO/VMD certification tests.
3
Jan–Feb 2026 · CEN scheduling attempts (multiple)
Three Failed CEN Test Date Requests — Jan 28–30, Feb 11, Feb 23–25
Vector Renewables (Fabiola) submitted multiple CEN test date requests: first for Jan 28–30, then rescheduled to Feb 23–25 after delays. Meanwhile, iEnergia (Emilio) was actively monitoring PPC control behavior and working with Diego Allende on each open item — voltage signal, frequency, reactive power. Emilio maintained cautious optimism but noted each remaining issue as it appeared.
4
Feb 10–11, 2026 · GPM "last item done"
Diego Allende: "Ya hicimos la modificación — devolveremos el proyecto a Customer Success"
After Emilio requested the voltage phase-to-phase modification and irradiance signal addition, Diego Allende confirmed the changes were made. He declared this was the last pending item and transferred the project back to GPM's Customer Success team. Emilio received a "second GPM confirmation" that frequency and voltage controls were enabled.
"Ya hicimos la modificación en el voltaje fase a fase. Considerando que esto era lo último pendiente, devolveremos el proyecto al área de Customer Success de GPM."
— Diego Allende (GPM/DNV) · Feb 10/11, 2026
Emilio's careful response (Feb 12): "Recibimos una segunda confirmación por parte de GPM indicando que los controles quedaron habilitados (frecuencia ok, voltaje hoy o mañana). De todas formas, para evitar cualquier confusión y considerando los antecedentes previos, utilizaremos parte del primer día para realizar una verificación interna y forzar los casos que sean necesarios." — Emilio was already aware that prior confirmations had not held up under real test conditions.
Feb 23, 2026 · Test day — first attempt
Fabiola Tells GME "All Controls Working" — GME Tests Fail
On the day of the CEN-authorized tests, Fabiola (Vector) sent GME (Nicolas Perez) a confirmation that all controls were working, with screenshot attachments. GME agreed to attend. The tests proceeded — and failed.
"Buen día Nicolás. Te confirmo todos los controles funcionan correctamente, de acuerdo con lo solicitado, adjunto print de verificación. Dicho esto y dado que tenemos autorización a contar de hoy para realizar las pruebas con el CEN, agradezco me puedas confirmar vuestra disponibilidad para retomar las mismas."
— Fabiola Silva (Vector Renewables) → GME · Feb 23, 2026
Emilio reported the same day: "no se realizó la prueba de control con GME según lo acordado previamente" and noted the test day was already running behind. The control tests as agreed with GME were not completed.
!
Feb 11–23, 2026 · GME's pattern response
GME: "Ya Habíamos Tenido Confirmación — Y la Realidad Mostró Que No Fue Así"
This was not the first time GME had received a "controls working" confirmation that turned out to be incorrect. Nicolas Perez made this explicit when Fabiola pushed for the Feb 23 test dates — and demanded screenshot proof before agreeing to attend again.
"Nosotros tenemos disponibilidad, pero debemos tener confirmación de que los controles funcionan correctamente. Ya habíamos tenido confirmación de que funcionaban ok y la realidad mostró que no fue así. Favor de enviarnos capturas de cambios de referencias de tensión y potencia reactiva."
— Nicolas Perez (GME) · Feb 11/12, 2026
GME also clarified: "El alcance específico de GME, no es el que definimos nosotros sino el que está establecido considerando la normativa del CEN para las pruebas de entrada en operación de un nuevo generador renovable... el parque también tiene que tener control de reducción de potencia ante sobrefrecuencia." — No flexibility on scope.
!
Mar 11, 2026 · The definitive diagnosis
Diego Allende Returns from Vacation — Root Cause Confirmed: No Real POI Meter
After his vacation (Feb 18 – Mar 2), Diego Allende (GPM/DNV) returned and made the critical statement that explains everything. Having consulted GPM's PPC specialists, he delivered the definitive diagnosis:
"Los especialistas nos comentaron que, al no tener un medidor en el POI, el PPC no funciona correctamente.

Hay que recordar que desde un inicio se planteó que la idea de configurar el PPC con un medidor ficticio era regular el curtailment del parque, y que sería un problema pasar las exigencias del coordinador sin un sistema en lazo cerrado. Es por eso que solo se configuró la medición ficticia de potencia activa y reactiva del medidor, y se mantuvieron valores fijos para voltaje, FP y frecuencia."
— Diego Allende (GPM/DNV) · Mar 11, 2026
This is the definitive statement. The "fictitious meter" configuration — always understood as a temporary workaround — could regulate active power curtailment but could NOT pass CEN EO/VMD certification because closed-loop control on voltage, frequency, and reactive power required a real physical meter signal from the POI. Without that, the controls ran on fixed simulated values.
!
Mar 31, 2026 · The mandate
Consequence: GPM Formally Declares Fiber Optic Mandatory
The logical conclusion of Diego's Mar 11 analysis: to have a real POI meter signal, you need a direct fiber optic connection from the meter in Paño E5 to the PPC. 4G/RS485/Ethernet paths cannot provide the deterministic, real-time signal required. GPM declared FO mandatory — and the 2.5-month clock to the Jun 11 installation began.

Key Email Chain: EO/VMD Testing Thread

Why the Tests Failed — In One Sentence

The PPC was configured with a "fictitious meter" (simulated values from inverter averages) which could manage curtailment but could not run the closed-loop voltage, frequency, and reactive power controls that GME/CEN require for EO/VMD certification — because those controls need a real-time signal from a physical meter at the POI.

What Diego's Email Means for iEnergia's Position

Diego Allende's Mar 11 email confirms that the fictitious-meter configuration was "planned from the start" as a curtailment workaround — GPM's own decision, not iEnergia's. iEnergia (Emilio) was actively working with Diego on every PPC control issue as it arose: voltage signal options, frequency averaging, VQ control. When Diego identified the root cause, iEnergia immediately communicated it to Obton and the team. The fiber optic requirement is GPM's technical finding, not iEnergia's scope failure.

Technical Explanation

The Open Loop Problem

GPM said the meter integration was "working" — and it was, for SCADA monitoring. But the CEN Coordinator requires a fundamentally different connection for PPC certification. Understanding this distinction is key to understanding the entire project delay.

Path A: SCADA Monitoring (WORKING ✓)
ION 8650
RS485 port
USR Gateway
192.168.1.7:502
GPM SCADA
reads every 5min
Result: Meter values visible, polling works, GPM confirms "everything working"
BUT: Read-only. 5-minute polling interval. No deterministic timing. Non-certifiable for CEN PPC control.
Path B: PPC Control Loop (BLOCKED ✗)
PPC Controller
needs meter input
RS485 / 4G
Modbus TCP path
CEN Cert.
won't accept
CEN Coordinator will not certify a PPC that relies on 4G/Modbus TCP as its metering feedback path
Deterministic latency, guaranteed availability, and physical isolation from network interference are required.
Why RS485 / Modbus TCP Fails for PPC
  •   4G / WAN dependency
    RUTX11 uses Movistar 4G. Network interruptions (like May 28 outage) break the path. CEN requires ≥99.9% deterministic availability.
  •   5-minute polling ≠ real-time control
    SCADA polls every 5 minutes. PPC needs sub-second metering feedback to react to grid events. Completely different use case.
  •   Meter Ethernet port locked by CGE
    Port 10.13.19.38 is CGE's connection for CEN reporting (SITR). Cannot be repurposed. We don't have credentials and CGE manages this network segment.
  •   No physical isolation
    RS485 is shared cabling. CEN design criteria requires control systems be physically isolated from force/power systems — same reason FO route was rejected first time.
Why Fiber Optic Solves It
  •   Dedicated physical medium
    ZTT ADSS-SS-URBANO G.652D monomode — no shared cabling, no wireless dependency.
  •   Deterministic, low-latency link
    Sub-millisecond transmission, no 4G jitter. Satisfies CEN Coordinator PPC certification requirements.
  •   Compliant with CGE design criteria
    Segregated conduit, 2 new chambers — fully separated from MT cables. Approved June 3, 2026.
  •   GPM can use as PPC input
    With FO, GPM closes the PPC control loop. ~2 hours of programming remain (per Alexander Jun 8) — then ready for CEN tests.
The "Open Loop" in Plain Language

GPM's SCADA was reading the meter and confirmed values were correct — hence "everything is working." But a closed PPC control loop requires the meter to be the active feedback input that the controller acts upon in real time. The RS485/4G path provided readings but not a certifiable control input. There was no fix for this short of a direct fiber connection — which is exactly why GPM mandated it, and why it was not optional.

Stakeholder Analysis

Who Did What — Explicit Role Clarity

A factual record of each party's actual technical contribution, sourced directly from email threads. Vector Renewables appears in every email chain as CC — but with zero technical input at any point in the process.

Technical Involvement by Party
Party Role Technical Input Communications Record
iE
iEnergia
Emilio Toledo, Adan Colina
O&M / Technical Active & decisive. Documented dual-network architecture, diagnosed May 28 comms loss, explained RS485/Ethernet constraints, clarified why meter Ethernet port cannot be repurposed, provided all technical specs to GPM within minutes of request. Sends, responds, diagnoses. Primary technical voice in all threads.
OB
Obton
Alexander Carthew (alc@obton.com)
Client / Coordinator Coordinates between parties. Escalated to CGE on emergency basis (Apr 30). Reactivated GPM after FO decision (Jun 8). Business decision authority. Hub of all external communication. Relies on iEnergia for all technical answers.
GP
GPM / GreenPowerMonitor
Emmanuel Honorato, Daniel
PPC Integrator Confirmed SCADA integration working (RS485 monitoring). Declared FO mandatory for PPC (Mar 31). Ticket #89466 — modification session Jun 15. ~2hrs programming remaining. Technical authority on PPC requirements. Changed requirements in Mar 2026.
CG
CGE (Adonis Fuenzalida)
Substation owner
Regulator/Owner Rejected first FO route (May 5) citing "Criterio de Diseño de Subestaciones." Approved redesigned route (Jun 3) with segregated conduit and 2 new chambers. Gate-controls all physical work inside S/E El Peumo.
RN
RNE / Reliable
centrodecontrolrne@reliable.cl
Control Center Installed RUTX11 (Oct 2025, via Verbux/Juan Cuevas). Manages 10.13.19.x network segment and meter Ethernet for SITR/CEN reporting. Holds router credentials. Responsible for their own network segment. Responsive to iEnergia escalation (May 28).
VR
Vector Renewables
Fabiola Silva (fsilvaberrios@vectorenewables.com)
Asset Management None. Fabiola Silva appears exclusively as CC recipient in every email thread. No technical questions sent. No answers provided. No input on FO, meter, GPM, or CEN. Active only in scheduling meetings for VMD and generation parameter studies — not in the integration process. CC only. No to/from. Zero technical contribution.
Vector Renewables — Asset Management, Not Technical

In every email thread covering meter integration, fiber optic, GPM, comms loss, CGE approval, and CEN testing, Fabiola Silva (Vector Renewables) appears only in the CC field. No emails were sent from Vector, no technical questions were raised, and no answers were provided. Vector's role is asset management — they do not have visibility into or understanding of the technical integration that iEnergia is responsible for.

GPM Position History

GPM: From "Working" to "FO Mandatory"

GPM's stated position evolved during the project. Understanding this sequence explains why the project seemed on track, then suddenly wasn't.

Phase 1 · Oct 2025 – Mar 2026
"Everything Is Working"

GPM confirms the meter is visible in SCADA. ION 8650 values being polled via USR RS485→Ethernet gateway at 192.168.1.7:502, unit 103. Readings confirmed accurate. SCADA element LLY_POI / ION_8650 operational. This referred to monitoring only.

Phase 2 · March 31, 2026
"FO Is Mandatory for PPC"

GPM declares that the existing communication path is not viable for PPC control-loop certification. Fiber optic is required — not optional. This arrives as a surprise at a late stage. Alexander forwards to iEnergia, who immediately provides technical documentation of why the current paths cannot substitute for FO.

Phase 3 · June 8 + 15, 2026
"~2 Hours of Programming Left"

After FO installation confirmed, Alexander reactivates GPM (Jun 8). GPM confirms only ~2 hours of programming remain to complete the PPC modification (ticket #89466). Session scheduled June 15 with Emmanuel Honorato. CEN tests follow June 18.

Why GPM Said "Working" Then Changed Position

There is no contradiction in GPM's statements. SCADA monitoring was working and continued to work throughout. When GPM said "everything working," they meant the data integration for monitoring purposes. The PPC certification requirement (active meter input for closed-loop control) is a different system requirement that only became relevant as the CEN Coordinator test date approached. GPM's mandate for FO was a technical requirement escalation, not a correction of an error.

CEN Coordinator

The CEN Audit — No Second Chances

The CEN Coordinator connection tests are a formal regulatory audit. There is no tolerance for "we'll fix it" responses during the test window. This strictness is not unusual — it is how all PMG certifications work in Chile.

CEN Audit Characteristics
  • Zero tolerance for partial compliance — system must meet all requirements on test day
  • No "pending fix" approvals — failing one test means rescheduling the entire audit
  • Strict scheduling delays — rescheduling after a failed test can mean weeks or months of wait
  • Coordination with grid operator required — tests require CEN coordination, cannot be done unilaterally
Why We Could Not "Just Try" with Existing Setup

If we had attempted CEN Coordinator tests with the RS485/Modbus TCP path, the test would have failed on PPC metering input requirements. This would have reset the clock on CEN scheduling — likely delaying the plant's certification by months. Waiting for the FO and doing it right was the only rational path.

What Must Pass on June 18
  • PPC Active Power Control Test
    Meter must be live PPC input via FO link. GPM modification must be complete (Jun 15 session).
  • Power Factor / Reactive Control Test
    CEN will test reactive power response — also requires certified meter path.
  • SCADA Telemetry to Coordinator
    Real-time data reporting to CEN systems must be confirmed operational.
  • Fiber Optic Physical Connection
    Complete. Installed Jun 11–12, 2026 by FENIX IO SPA. ZTT ADSS-SS-URBANO G.652D.
  • CGE Route Authorization
    Approved June 3. Segregated conduit, 2 new chambers, no MT cable sharing.
iEnergia Response Record

iEnergia Response Times

Every technical question or incident that reached iEnergia was answered promptly and with complete technical detail. This is the documented record from email timestamps.

<30min
Jun 10 reply
Full network architecture documented: ION 8650 dual-path, RS485 gateway, Ethernet port constraints
Alexander forwarded GPM's IP request at ~17:54 Jun 10. iEnergia (Emilio) replied with complete technical breakdown including RS485 path params, why Ethernet port 10.13.19.38 cannot be repurposed (CGE locked), what RNE/RUTX11 would need to provide, and full address schema. Reply within minutes of receiving the request.
Same day
May 28
May 28 comms loss: iEnergia identified fault in RUTX11, not in meter or gateway
When connectivity was lost, iEnergia confirmed plant equipment was online on their side (USR gateway, meter) and correctly diagnosed the issue as being in RNE's RUTX11. Adan Colina notified RNE immediately. Router reset by RNE resolved the issue.
Ongoing
All GPM queries
All GPM technical queries routed through iEnergia — answered without delay
GPM's technical questions about the ION 8650 network configuration, gateway parameters, and communication paths were all answered by iEnergia. No query has been left open or delayed. The 2.5-month delay was in regulatory approval (CGE) and civil works scheduling — not in iEnergia's technical response.
iEnergia's Track Record in This Project

iEnergia's role in every technical dimension of this project has been proactive and responsive: meter integration monitoring (live since Oct 2025), incident diagnosis (May 28, resolved same day), network documentation (complete specs sent within 30 minutes of request), and ongoing liaison with GPM and RNE. The 2.5-month delay was outside iEnergia's control — in CGE's design-criteria review process.

Communications Log

Key Email Excerpts

Verbatim excerpts from the actual email chains, in chronological order. All quotes are sourced directly from the project email threads.

Thread 1 · GPM Declares FO Mandatory (Mar–Apr 2026)
Thread 2 · CGE Rejects First Route (May 5, 2026)
Thread 3 · May 28 Comms Loss — iEnergia Diagnoses RUTX11 (May 28, 2026)
Thread 4 · CGE Approves Redesigned Route (June 3, 2026)
Thread 5 · Alexander Reactivates GPM — FO Decision Confirmed (June 8, 2026)
Thread 6 · iEnergia Responds with Full Technical Architecture (June 10, 2026)
Technical Architecture

ION 8650 Dual-Network Architecture

Two completely separate network segments serve the meter — one for O&M/SCADA (iEnergia's side), one for CGE/CEN reporting (RNE's side). Neither can substitute for the other, and neither can substitute for a direct FO link for PPC control.

POI LAN · 192.168.1.0/24 · iEnergia CGE/RNE SEGMENT · 10.13.19.0/24 ION 8650 POI Cabinet S/E El Peumo E5 RS485 + Ethernet USR RS485→ETH 192.168.1.7:502 Unit ID 103 MONITORING ✓ RS485 COM4 9600 8N1 GPM SCADA LLY_POI / ION_8650 5-min poll · monitoring only FIBER OPTIC (NEW) ZTT ADSS G.652D · Installed Jun 11 · PPC Input ✓ PPC Controller Needs closed-loop meter input via FO RUTX11 (RNE) 10.13.19.x · 4G WAN Movistar · SITR/CEN Not PPC-certifiable ✗ Ethernet 10.13.19.38 CGE-locked · cannot repurpose CEN Coordinator SITR telemetry strict audit · Jun 18
Green Path — Working (Monitoring)

USR RS485→Ethernet → GPM SCADA. Operational since Oct 2025. 5-minute polling. Confirmed working — but monitoring only, not PPC control input.

Orange Path — FO (New, PPC)

Fiber optic installed Jun 11–12. This is the path GPM needs for PPC modification (Jun 15) and CEN Coordinator tests (Jun 18). The only certifiable path.

Purple Path — RNE (CGE-Locked)

RNE's RUTX11 on 10.13.19.x. CGE locked, RNE manages, 4G-dependent. Cannot be used as PPC input. Caused May 28 outage when router needed reset.

Pending Tasks

Action Plan

Items organized by horizon. Owners marked where confirmed.

7-Day by 19 Jun 2026
CRITICAL
GPM PPC Modification Session
Mon 15 Jun · Emmanuel Honorato (GPM) · #89466 · ~2hrs work
CRITICAL
CEN Coordinator Connection Tests
~Thu 18 Jun · Alexander Carthew (Obton) + CEN · no-fix window
PENDING
Confirm RUTX11 exact LAN IP
iEnergia → RNE / centrodecontrolrne@reliable.cl
PENDING
Obtain meter network credentials for .38 access
iEnergia → RNE
15-Day by 27 Jun 2026
PENDING
Validate GPM PPC polling post-FO activation
iEnergia + GPM · confirm closed loop via FO
PENDING
RNE credentials handover documentation
RNE → Obton/iEnergia
PENDING
CEN certification confirmation received
CEN → Obton · post Jun 18 tests
30-Day by 13 Jul 2026
REVIEW
Fiber optic performance audit
iEnergia · first 30 days post-activation
REVIEW
RS485 monitoring path continuity check
iEnergia · confirm both paths stable in parallel
REVIEW
Post-certification lessons learned
iEnergia + Obton · documentation for next PMG
Contact Directory

Project Contacts

All parties involved in the meter integration and CEN certification process.

Name Organization Role in Project Contact Technical Involvement
ET
Emilio Toledo
iEnergia O&M Technical lead: meter architecture, GPM liaison, comms docs emilio.toledo.g@ienergiachile.com ACTIVE LEAD
AC
Adan Colina
iEnergia O&M O&M operations, May 28 incident response, RNE comms adan@ienergiachile.com ACTIVE
ALC
Alexander Carthew
Obton Client Client coordinator. Escalated to CGE, reactivated GPM, scheduled CEN tests alc@obton.com COORDINATOR
EH
Emmanuel Honorato
GPM PPC GPM technical contact · PPC modification ticket #89466 GPM support ACTIVE
AF
Adonis Fuenzalida
CGE Regulator CGE substation authority. Rejected first FO route. Approved revised route Jun 3. CGE internal REGULATORY
RNE
Centro Control RNE
RNE / Reliable Control Center Manages RUTX11, meter Ethernet segment (10.13.19.x), SITR/CEN reporting centrodecontrolrne@reliable.cl COORDINATION
FS
Fabiola Silva
Vector Renewables Asset Mgmt Asset management. CC on all emails. No technical input at any point in this project. fsilvaberrios@vectorenewables.com CC ONLY
Risk Register

Open Risks

Remaining risks after FO installation. Most major blockers have been resolved.

RiskSeverityStatusOwner / Mitigation
GPM PPC session doesn't complete Jun 15
If session is delayed, CEN tests (Jun 18) cannot proceed — rescheduling risk is weeks/months
HIGH OPEN GPM (Emmanuel Honorato) · ~2hrs remaining per Alexander Jun 8
CEN test fails — PPC not fully configured
CEN does not allow mid-test fixes. Failure means full rescheduling.
HIGH OPEN GPM modification must be 100% complete before Jun 18. No partial compliance.
RNE credentials not shared for meter Ethernet config
Cannot reconfigure 10.13.19.38 without RNE cooperation
MED OPEN iEnergia to request via Obton → RNE channel
RUTX11 repeats May 28 outage
4G router dependency — another reset would interrupt CEN-side reporting
MED OPEN RNE to monitor. FO path for PPC is independent of RUTX11.
Fiber optic physical integrity post-install
First 30 days after installation — verify no damage, attenuation within spec
LOW MONITORING iEnergia 30-day post-activation audit