iE
PMG LlancayObton · iEnergia O&M
ON TRACK
GPM Session Jun 15
PMG Llancay · Executive Briefing · Jun 2026

Meter Integration
Status Report

ION 8650 dual-network architecture confirmed and operational. GPM PPC modification session scheduled. CEN coordinator tests imminent.

Comms Restored
3
Days to GPM Session
6
Days to CEN Tests
2
Open Risks
Press ESC or click Present to exit
Executive Dashboard · iEnergia Internal

PMG Llancay
Meter Integration

S/E El Peumo, Paño E5 · ION 8650 at POI Cabinet · GPM PPC ticket #89466 · O&M: iEnergia · Client: Obton

Last updated: 12 Jun 2026  ·  Prepared by: Emilio Toledo, iEnergia
✓ Live
GPM Comms Status
USR gateway 192.168.1.7:502 · Unit 103
3
Days to GPM PPC Session
Mon 15 Jun 2026 · GPM / DNV
6
Days to CEN Tests
Thu 18 Jun 2026 · Coordinator
✓ Done
Fiber Optic Installed
11 Jun 2026 · S/E El Peumo internal
#89466
GPM Ticket
Modificación PPC · Emmanuel Honorato
2
Open Risks
RNE credentials · Meter Ethernet locked
Project Timeline

Integration Roadmap

Key milestones from RNE installation through CEN coordinator certification.

Oct 2025
RNE RUTX11 Installed
Verbux / Juan Cuevas
28 May 2026
Comms Loss & Recovery
RUTX11 reset · RNE
10 Jun 2026
Network Docs Sent
iEnergia → Obton/GPM
11 Jun 2026
Fiber Optic Installed
S/E El Peumo
15 Jun 2026
GPM PPC Modification
GPM / DNV · #89466
~18 Jun 2026
CEN Coordinator Tests
CEN · Obton
TBD
Integration Certified
CEN Approval
Completed Work

What's Been Done

All verified completed items grouped by category.

Network & Connectivity

USR RS485→Ethernet Gateway Configured
192.168.1.7:502 · Unit ID 103 · RS485 COM4 9600 8N1
Oct 2025 · Verbux / iEnergia
Teltonika RUTX11 Router Installed
RNE segment 10.13.19.x · Movistar 4G WAN · polls meter at .38
Oct 2025 · Verbux (Juan Cuevas)
Fiber Optic Line Installed at Substation
Internal FO within S/E El Peumo perimeter
11 Jun 2026
Meter IP Inventory Documented
Both network segments fully mapped and validated
Jun 2026 · iEnergia

Communication & Incident Response

Comms Loss Incident Resolved
May 28 outage traced to RUTX11 needing reset; RNE notified
May 2026 · iEnergia + RNE
Full Technical Specs Sent to Obton/GPM
ION 8650 network details, gateway params, RNE path documented
10 Jun 2026 · Emilio Toledo → Alexander Carthew

SCADA & PPC

GPM PPC Ticket Opened
Ticket #89466 (Modificación PPC) with GPM/DNV support
Jun 2026 · Emmanuel Honorato (GPM)
SCADA Element Identified
LLY_POI / ION_8650 element in GPM PPC Monitoring
Jun 2026
GPM PPC Session Scheduled
Monday 15 Jun 2026 — modification session confirmed
Jun 2026 · GPM / DNV

Coordination & Documentation

CEN Coordinator Tests Scheduled
~Thu 18 Jun 2026 — connection tests with CEN
Jun 2026 · Obton / Alexander Carthew
RNE Integration Architecture Confirmed
RUTX11 polling 10.13.19.38 for SITR/Control Center confirmed
Oct 2025 emails · Mario Mejias (RNE)
Dual-Network Architecture Documented
POI LAN (192.168.1.0/24) vs CGE/RNE segment (10.13.19.0/24) fully mapped
Jun 2026 · iEnergia
Pending Tasks

Action Plan

Items organized by horizon. Owners marked where confirmed.

7-Day by 19 Jun 2026
CRITICAL
GPM PPC Modification Session
Mon 15 Jun · Emmanuel Honorato (GPM)
CRITICAL
CEN Coordinator Connection Tests
~Thu 18 Jun · Alexander Carthew (Obton) + CEN
PENDING
Confirm RUTX11 exact LAN IP
iEnergia → RNE / centrodecontrolrne@reliable.cl
PENDING
Obtain meter network credentials
For 10.13.19.38 config access · iEnergia
15-Day by 27 Jun 2026
PENDING
Validate GPM polling 5-min interval post-modification
iEnergia + GPM
PENDING
RNE credentials handover documentation
RNE (Reliable) · credentials held by centrodecontrolrne
PENDING
Fiber optic connectivity test end-to-end
iEnergia field team · S/E El Peumo
NICE-TO-HAVE
Document fallback procedure for RUTX11 reset
iEnergia (Adan Colina)
30-Day by 12 Jul 2026
PLANNED
CEN integration certification received
CEN / Obton
PLANNED
Update O&M procedures with meter network map
iEnergia (Emilio Toledo)
PLANNED
Set up monitoring alert for comms loss (repeat of May 28)
iEnergia
PLANNED
Quarterly review with Obton / Alexander Carthew
iEnergia → Obton
Stakeholder Matrix

Key Contacts

All parties involved in the Llancay meter integration.

Name Organization Role Contact Status
ET
Emilio Toledo
iEnergia PM / QA · O&M Lead emilio.toledo@ienergia.cl Active
AC
Alexander Carthew
Obton Client Representative alc@obton.com Active
EH
Emmanuel Honorato
GPM / DNV SCADA / PPC Support — (ticket #89466) Session Jun 15
FS
Fabiola Silva
Vector Renewables Technical Advisor to confirm Advisor
ADC
Adan Colina
iEnergia Field Operations adan@ienergiachile.com Active
RNE
Centro de Control RNE
Reliable (RNE) Grid Control Center centrodecontrolrne@reliable.cl Pending creds
JC
Juan Cuevas
Verbux RUTX11 Installation to confirm Installer
MM
Mario Mejias
RNE RNE Technical Contact to confirm RNE
DF
Daniel Friedman
iEnergia iEnergia Internal to confirm Internal
Technical Architecture

Network Diagram

ION 8650 dual-network architecture at S/E El Peumo, Paño E5.

POI LAN · 192.168.1.0/24 RNE / CGE SEGMENT · 10.13.19.0/24 ION 8650 LLY_POI · Paño E5 POI Cabinet · S/E El Peumo RS485/COM4 Ethernet USR Gateway 192.168.1.7:502 Unit ID 103 GPM SCADA Modbus TCP · Poll 5 min Modbus TCP Meter Ethernet 10.13.19.38 CGE/CEN locked ⚠ Recloser E5 10.13.19.39 Form 6 · Paño E5 RUTX11 Router 10.13.19.xx (LAN) Movistar 4G WAN · Verbux polls .38 Movistar 4G RNE SITR CGE / CEN Reporting locked ─── Modbus TCP (GPM path) - - - RS485 / Ethernet ⚠ = locked (no credentials) ○ = to confirm
GPM Path (Modbus TCP) 192.168.1.7:502 · Unit ID 103 RS485 COM4 · 9600 8N1 Poll interval: 5 min
Meter Own Ethernet IP: 10.13.19.38 Purpose: CGE/CEN reporting Status: LOCKED — no credentials Default password not working
RNE RUTX11 LAN: 10.13.19.xx to confirm WAN: Movistar 4G Polls: 10.13.19.38 Managed by: RNE / Reliable
Infrastructure

Fiber Optic Installation

FO line installed 11 Jun 2026 at S/E El Peumo. Recommended follow-up steps for full integration.

Installation Checklist

  • FO cable installed within substation perimeter
    S/E El Peumo · Completed 11 Jun 2026
  • End-to-end fiber connectivity test
    Field test with OTDR or loopback · Pending
  • FO patch from switchgear cabinet to meter
    Physical connection at ION 8650 FO port · Pending
  • Switch/media converter configured
    If required for FO→Copper transition · Pending
  • Integrate FO into primary comms path
    Replace or supplement 4G RUTX11 for RNE path · Recommended
  • Document FO route and splice points
    As-built drawing · Recommended

⚡ Recommendation

The installed FO link should be evaluated as a primary communication path for the RNE SITR connection, replacing the current Movistar 4G dependency. The May 28 outage was caused by the RUTX11 needing a reset — a wired FO path would eliminate this failure mode.

The Modbus TCP path via USR gateway (192.168.1.7) is on a separate network segment and is not affected by this improvement.

ACTION OWNER
iEnergia + RNE (Reliable)
Coordinate FO path integration with centrodecontrolrne@reliable.cl
Testing Dashboard

Integration Test Matrix

All integration tests tracked by status. Updated as sessions complete.

Test / Verification
Status
Owner
Date
USR Gateway Modbus TCP reachability
192.168.1.7:502 · Unit 103 responds
PASS
iEnergia
Jun 2026
GPM 5-min poll — data received
LLY_POI / ION_8650 element in SCADA
PASS
GPM / Emmanuel H.
Jun 2026
RUTX11 online & polling meter
10.13.19.xx → 10.13.19.38 confirmed
PASS
RNE
Oct 2025
GPM PPC modification — post-session validation
Verify modified PPC params accepted by SCADA
SCHEDULED
GPM / iEnergia
15 Jun 2026
CEN coordinator connection test
Official certification test with CEN
PENDING
CEN / Obton
~18 Jun 2026
Fiber optic end-to-end connectivity
FO path test after patching to meter port
PLANNED
iEnergia field
TBD
Meter Ethernet (10.13.19.38) access test
Requires credentials from CGE/RNE — blocked
BLOCKED
iEnergia + RNE
TBD
Comms failover test (4G → FO)
Simulate 4G loss, confirm FO path takes over
PLANNED
iEnergia + RNE
Post FO integration

Integration Progress

Network Connectivity100%
GPM SCADA Integration75%
CEN Certification30%
Fiber Optic Integration20%
Overall Integration55%
Risk Register

Risks & Decisions

Active risks and key decisions made during the integration.

Risk Register

Risk Severity Status Mitigation
Meter Ethernet (10.13.19.38) credentials unavailable — no access to reconfigure CGE path High Open Request from RNE/CGE. GPM path unaffected.
RUTX11 4G link instability (repeat of May 28 outage) Medium Monitor Document reset procedure. FO as backup path.
GPM PPC session result unknown until Jun 15 Medium Imminent Emilio Toledo present in session. Fallback: extend ticket.
RUTX11 exact IP unconfirmed (10.13.19.xx) Low Open Request from centrodecontrolrne@reliable.cl
CEN test delay if GPM session fails Medium Contingency Notify Obton/Alexander Carthew immediately if GPM blocked.

Decision Log

Oct 2025
RUTX11 installed by Verbux (not iEnergia)
RNE (Reliable) contracted Verbux/Juan Cuevas for installation. Credentials remain with RNE, not iEnergia.
Jun 2026
GPM path: USR gateway, not meter Ethernet
Decision to route GPM Modbus TCP via 192.168.1.7:502 (separate POI LAN) since meter Ethernet (10.13.19.38) is locked by CGE and cannot be reconfigured.
10 Jun 2026
RUTX11 IP listed as 10.13.19.xx (unconfirmed)
Draft had .1 but changed to .xx per iEnergia PM — exact address not confirmed with RNE. To resolve before CEN tests.
11 Jun 2026
FO to be evaluated as RNE primary path
iEnergia recommendation: replace 4G RUTX11 dependency with FO post-installation. Decision pending RNE coordination.
Data Visualization

Integration at a Glance

Integration Progress by Area

Test Status Breakdown

Timeline — Days to Milestones (from Jun 12)

Risk Severity Distribution

PMG Llancay — Executive Dashboard
iEnergia O&M · Obton Client · Confidential Internal Document
to confirm = data pending verification
Data sourced from project emails Jun 2026 · iEnergia internal
Contact: emilio.toledo@ienergia.cl